Payment Schedule - Suhool (Salam 2 villa)

  Amount Schedule Expected date

1

10% of purchase price

First payment at time of signing contract

Signing of contract

2

15% of purchase price

On completion of foundation

DCC plus 2 to 3 months

3

15% of purchase price

On completion of ground floor roof

Date above plus 2 to 3 months

4

10% of purchase price

Completion of block-work

Date above plus 2 to 3 months

5

10% of purchase price

On completion of mechanical and electrical installation

Date above plus 2 to 3 months

6

15% of purchase price plus costs of all extra work/additions

Start of finishing's (Plaster, tiles & paint)

Date above plus 2 to 3 months

7

10% of purchase price

Finishing (Doors, Windows & Sanitary)

Date above plus 2 to 3 months

8

15% of purchase price

Completion of construction

Date above plus 2 to 3 months

 

Definitions of Payment

Completion of foundation

The completion of casting the property's foundations as approved by developer and consultant.

Completion of ground floor roof

The completion of constructing the ground floor roof as approved by developer and consultant.

Completion of block-work

The completion of construction of the block wall inside the property as approved by developer and by the consultant.

Completion of mechanical and electrical installations

The completion of mechanical and electrical installations such as electrical conduits and water pipes as approved by developer and consultant

Start of finishing phase

The start of plastering and flooring works and the installation of ceramic tiles in bathrooms and kitchens as approved by developer and consultant.

Finishing

The installation of doors, windows and sanitary

Completion of construction

The completion of construction and commissioning; ready for housing as per standards and specifications and as approved by developer and consultant.

Payment Schedule - Suhool Villas (Salam 3, Salam 4)

  Amount Schedule Expected date

1

10% of purchase price

First payment at time of signing contract

Signing of contract

2

15% of purchase price

On completion of foundation

DCC plus 2 to 3 months

3

10% of purchase price

On completion of ground floor roof

Date above plus 2 to 3 months

4

15% of purchase price

Completion of 1st floor roof

Date above plus 2 to 3 months

5

10% of purchase price

Completion of block-work

Date above plus 2 to 3 months

6

10% of purchase price plus costs of all extra work/additions

On completion of 1st phase of mechanical and electrical installation

Date above plus 2 to 3 months

7

15% of purchase price

Start of finishing

Date above plus 2 to 3 months

8

15% of purchase price

Completion of construction

Date above plus 2 to 3 months

Definitions of Payment

Completion of foundation

The completion of casting the property's foundations as approved by developer and consultant.

Completion of ground floor roof

The completion of constructing the ground floor roof as approved by developer and consultant.

Completion of 1st floor roof

The completion of constructing the 1st floor roof as approved by developer and consultant.

Completion of block-work

The completion of construction of the block wall inside the property as approved by developer and by the consultant.

Completion of mechanical and electrical installations

The completion of mechanical and electrical installations such as electrical conduits and water pipes as approved by developer and consultant

Start of finishing phase

The start of plastering and flooring works and the installation of ceramic tiles in bathrooms and kitchens as approved by developer and consultant.

Completion of construction

The completion of construction and commissioning; ready for housing as per standards and specifications and as approved by developer and consultant.

Suhool Villas – Specifications 

 

Outer walls made up of concrete blocks, insulated and measuring 20X20X40 (15X20X40 cm internal walls)

External Walls

The structure of the concrete rules of armed and bridges and ground floor and Al-Leheis fields are underway and the columns and the roof, according to standard specifications, Iraqi and British B. S. and U.S. ASTM and schemes adopted and Advisory Office.

Structure

Is surveyor (لبخ) the walls with cement and sand after scattered sand and cement mortar, and the installation of the corners and grille and according to the specifications and drawings approved by the Advisory Office.

Plastering

And the foundation is placed, putty and paint the final two layers, according to the specifications and workmanship assets and plans approved by the Advisory Office..

Paint

The supplying and installing porcelain كرانيتى floors in the halls and the rooms and cuisine and is supplying and installing ceramic grounds and bathrooms walls and walls of good quality cuisine, and according to the specifications and plans and samples of approved consultative before

Bathrooms (Walls & Flooring)

The work surface tendencies by concrete surface to isolate light thermally and highlight the route rain water to its objections with the installation 4 M buffer Layer moisture, and replace the Kashi final surface layer, and work ( Hazarajat italics) of الكونريت aspects.

Surfaces

The supplying and installing الكربستون and المقرنص, according to specifications and plans adopted by Advisory Office .

Outdoor Pathways

The extension and installing gas network centrally located by الانابيب. *

Gas line

The supply lines and installed electricity wires inside the walls and ceilings by plastic pipes PVC and processing and installed electricity switches and electrical outlet and boycotted the session main electrical ( MDB ) of European origin, and include التاسيسات Forum-Multimedia event and television point and heater and air conditioners and fans and lighting and power outlet, according to the plans approved by advisory and feed electricity residential unit by national electricity.

Electricity

Include the supply and the installation of pipes PPR Extreme للحار and cold and replace the bathtub with a blender and shower in main bathroom and a seat in western and laundry service and in a bathroom guests a seat in western and laundry with additional guest laundry and in the bathroom additional hot with a seat in western and laundry service and bidet in all the bathrooms, and, according to the plans approved by consultant

Sanitary ware & bath accessories

supply and install upvc pipeline with the necessary work of Knowledge", which covers with railways and according to the plans approved by Advisory Office

Sewage

Main entrance door and iron is made of acrylic panels and interior doors of wood.

Doors

supply and install upvc double glazed windows heat shield and the supply and installation tray quarry.

Windows

*The Developers retain the right to change or alter the finishing work or specifications whenever necessary and in accordance with the contract and contract terms and conditions

 

 

 

The credibility of the developers coupled with the achievements of the members of the Board of Directors form the first guarantee for buyers, apart from the following guarantees:

  • The Payment Plan is linked to progress of construction.
  • A preliminary registration certificate issued by the Department of Real Estate Registration in the Governorate of Dhi Qar will remain valid until the buyer receives an ownership deed upon completion of construction.
  • A certificate will be issued by the Consultant upon completion of every stage of construction, together with receipts for every payment.
  • The buyer will be informed of developments, and work in progress on site through news bulletins, emails, and pictures on the company’s website.
  • A visit to the site location can be arranged for buyers with prior appointment, in order to witness work in progress first-hand.
  • A Sales and Purchase agreement authorised by Dhi Qar Investment Commission guarantees the rights of the buyer.
  • Dhi Qar Investment Commission officially endorses Liwan, while the Governor of Dhi Qar offers his blessing and patronage.
  • There is a permanent Sales Centre for the Liwan project in Al Naseriyah, where buyers can always communicate with the company’s management.

Please read the following rules and regulations to be aware of the terms and conditions for ownership in Liwan:

Sale and Purchase contract
Terms of contract
Real estate rules and regulations

A house you have always dreamt of...

We are well aware of the fact that you are not just looking for a house, but for a home that reflects your inner self, your personality, your lifestyle, as well as all your traditions and values. 

How to buy in Liwan? 

»   'Suhool' Payment Schedules - Villa Salam 2
»   'Suhool' Payment Schedules - Villas Salam 3 & 4
»   Suhool Villas Specifications
»   Purchaser’s Rights
»   'Suhool' Rules & Regulations
Click Images For More Details >>>